• Project Location: Austria

  • Client: OMV Austria Exploration & Production GmbH

As part of the expansion of the existing central extraction station in Schönkirchen, an additional tank, pipes, and a separator were built to separate gas, water and oil.
All the necessary systems, such as piping, electrical engineering, instrumentation and control engineering, civil engineering, and steel construction were incorporated into the existing systems and integrated in terms of safety.
In September 2014, the project was honored with an OMV internal award (Golden Barrel) and technically and commercially completed.