• Project Location: Austria

  • Client: Wiener Wasserstoff GmbH, Austria

All design phases for the process planning and technical site supervision of the H2-generation, storage and erection of a hydrogen filling station as well as of the feed-in to the gas grid at the location Simmering Campus Wiener Netze GmbH was ordered by Wiener Wasserstoff GmbH.

To be erected:

  • 1x 3 MW PEM electrolyzer
  • 500 and 1000 bar compressors
  • Hydrogen filling station for cars and trucks
  • Trailer filling system
  • Connection to the natural gas network